For immediate release For more information
August 6, 2010 Public Works 485-3340
William Street Reduced To One Lane
Between Commercial and Goodwin Streets August 10
(VICTORIA, TEXAS) The City will reduce William Street to one-lane northbound between Goodwin and Commercial Streets Tuesday, August 10 to install water lines. Construction is expected to take approximately two weeks, weather permitting.
All businesses and parking lots in the work zone will remain accessible via alternate routes.
The City and contractor are working to reduce public inconvenience; however, drivers may experience delays in this area. Alternate routes are suggested when possible.
This construction is part of the $2,092,079.00 Downtown Water and Sewer Line Replacements (Phase I, Projects 3 & 4); this phase is estimated to be complete in seven months. The contractor performing the work is SER Construction Partners, LTD from Pasadena, Texas.
For more information, contact the Public Works Department at 485-3340.
|