FOR IMMEDIATE RELEASE FOR MORE INFORMATION
November 6 , 2009 Public Works 485-3340
William Street Narrowed From Constitution Street
to Juan Linn Street For Two Weeks.
(VICTORIA, TEXAS) The City will begin final paving of William Street Tuesday, November 10. The two-week construction will require narrowing William Street to one-lane northbound from Constitution Street to Juan Linn Street for approximately two weeks, weather permitting.
All businesses and parking lots in the construction zone will remain accessible via alternate routes; on-street parking will be prohibited.
To work safely and efficiently, the intersection of William Street and Santa Rosa Street will close completely for short periods. The intersection will reopen as soon as work is completed.
Although the City has taken measures to reduce the inconvenience to the public, drivers may experience major delays and should plan alternate routes when possible.
This construction is part of the $2,913,062 Downtown Water and Sewer
Line Replacements (Phase I, Projects 1 & 2). The contractor performing
the work is Triple B Services, LLP from Huffman, Texas.
For more information, contact the Public Works Department at 485-3340.
-30- |